Browse by Call Number


AIT Proj. no.MPM-CM-11-14
EPC commissioning strategy for gas pipeline project: a case study of Block B-O Mon Gas Pipeline Project
by Le Quang Son
AIT Proj. no.MPM-CM-11-15
Safety and health management in oil and gas construction projects: a case study of the Block B-O Mon Gas Pipeline Construction Project
by Pham Van Hung
AIT Proj. no.MPM-CM-11-16
Delay and contracy management in construction: a case study of administration centre and postgraduates trainings at Can Tho University
by Ho Chi Linh
AIT Proj. no.MPM-CM-11-17
Owner's project quality management: a case study of Northern PVOil station
by Doan Thai Duong
AIT Proj. no.MPM-CM-11-18
Quality management for building construction projects : a case study of residential area for Cantho University atudents
by Le Thanh Phieu
AIT Proj. no.MPM-CM-11-19
Development of quality management system in hospital construction project : a case study of the projects management board of investment and construcyion of Thoi Lai Districts
by Nguyen Tien Thuc
AIT Proj. no.MPM-CM-11-20
Delays in flood prevention projects : a case study of urban drainage project management unit
by Le Do
AIT Proj. no.MPM-CM-11-21
Pre-construction delay in building project development : a case study of Investco Babylon Projecy in Ho Chi Minh City
by Nguyen Tran Tuong Ly
AIT Proj. no.MPM-CM-11-22
Project management competency of a small contractor : a case study of Kien Tao Ltd., Company
by Tu Thien Tu
AIT Proj. no.MPM-CM-11-23
Business process management and key performance indicators in real estate construction
by Le Anh Thai
AIT Proj. no.MPM-CM-11-24
Effective planning & control of multiple projects : a case study of GR60 - Nokia stores chain in Viet Nam
by Nguyen Thai Son
AIT Proj. no.MPM-CM-11-25
Owner's project quality management system : a case study of Imperial An Phu Project in Ho Chi Minh, Viet Nam
by Nguyen Ngoc Thi
AIT Proj. no.MPM-CM-11-26
Variances in financial model between feasibility study and after design stage in Bau Sen Building Project
by Vo Thanh Phong
AIT Proj. no.MPM-CM-11-27
Risk factors in water environment improvement project : a case study of Bien Hoa City in Dong Nai Province
by Le Van Tuan
AIT Proj. no.MPM-CM-11-28
Cost escalation management in low-income apartment project
by Ngo Quoc Thai
AIT Proj. no.MPM-CM-11-29
Owner's EPC project management in power plant project : a case study of Nhon trach 2 Power Plant Project (750 MW)
by Nguyen Nhat Tai
AIT Proj. no.MPM-CM-11-30
Owner's tendering strategy to obyain a qualified contractor
by Nguyen Duc Huan
AIT Proj. no.MPM-CM-11-31
The delay factors during construction phase of a residential project in Binh Duong, Vietnam : case study of an Dien Urbanized Residential Commercial Zone
by Bui Viet Thi
AIT Proj. no.MPM-CM-11-32
Construction management in process piping installation : case study of Dung Quat Polypropylene Project
by Vu Van Tinh
AIT Proj. no.MPM-CM-11-33
Risk management of diaphragm wall construction affecting adjacent buildings : a case study of construction project in Ho Chi Minh City, Vietnam
by Huynh Thanh Quang