Simultaneous scheduling of quay cranes and yard cranes via particle swarm optimization | |
Author | Opas Ovasith |
Call Number | AIT Thesis no.ISE-10-34 |
Subject(s) | Cranes, derricks, etc.--Computer simulation Cranes, derricks, etc.--Mathematical models |
Note | A thesis submitted in partial fulfillment of the requirements for the degree of Master of Engineering in Industrial and Manufacturing Engineering, School of Engineering and Technology |
Publisher | Asian Institute of Technology |
Series Statement | Thesis ; no. ISE-10-34 |
Abstract | This thesis attempts to schedule quay cranes and yard crane simultaneously to find the optimal solutions for the whole system. The objective for the scheduling of yard cranes is to minimize the total travel distance of yard cranes in the container yard. The objective of the scheduling of quay cranes is to minimize turnaround time of vessel by maximizing the number of dual cycles. A Global, Local, Near Neighbor Particle Swarm Optimization algorithm (GLNPSO) is applied to solve the problem. The parameters of particle swarm optimization to be adapted include inertia weight, acceleration constants. A comparison is made between schedules obtained by scheduling QCs & YCs simultaneously and those obtained by scheduling them separately. It is shown that schedules obtained by scheduling QCs & YCs simultaneously are better than those schedules obtained separately of 90% confident interval. |
Year | 2010 |
Corresponding Series Added Entry | Asian Institute of Technology. Thesis ; no. ISE-10-34 |
Type | Thesis |
School | School of Engineering and Technology (SET) |
Department | Department of Industrial Systems Engineering (DISE) |
Academic Program/FoS | Industrial Systems Engineering (ISE) |
Chairperson(s) | Voratas Kachitvichyanukul |
Examination Committee(s) | Pisut Koomsap;Huynh, Trung Luong |
Degree | Thesis (M.Eng.) - Asian Institute of Technology, 2010 |