1
Contract administration in ODA - JICA fund project : a case study of Monywa-Ayataw-Shwebo road project | |
Author | Win Min Htut |
Call Number | AIT Proj. no.MPM-NPT-CM-15-03 |
Subject(s) | Contracts--Management--Case studies Project management--Case studies |
Note | A Project submitted in partial fulfillment of the requirements for the degree of Master of Engineering (Professional) in Construction Engineering and Infrastructure Management |
Publisher | Asian Institute of Technology |
Series Statement | |
Abstract | The government of the Republic of the Union of Myanmar, change to release centralization of government to private sector panticipation especially for the infrastructure construction . Current construction industry ws mostly excute by government organization. Myanmar‘s construction industry try to set up the new and perfect rules and regulations for private contractors.This case study are the practice of administration to pravite contractor , under control of Ministry of Construction. In the contract, there are a lot of strength and weakness. This report has been analysed based on the administration system and operation on theconstruction of the project . According to the practice, this report present the conditionsstant from before building process until to the end of the project |
Year | 2015 |
Corresponding Series Added Entry | |
Type | Project |
School | School of Engineering and Technology (SET) |
Department | Department of Civil and Infrastucture Engineering (DCIE) |
Academic Program/FoS | MPM - NPT - CM |
Chairperson(s) | Hadikusumo, B. H. W. |
Examination Committee(s) | Chotchai Charoenngam;Santoso, Djoen San |
Degree | Project (M. Eng.) - Asian Institute of Technology, 2015 |